View Cart

Indoor Environmental Air Quality 3.2 – Construction IAQ Management Plan – Before Occupancy

Intent:

  1. Reduce IAQ problems associated with Construction/Renovation process
  2. Help to sustain comfort and well-being of construction workers and building occupants

Implementation:

  1. Develop and implement an Indoor Air Quality (IAQ) Management Plan for pre-occupancy phase

Option 1: FLUSH-OUT

  • after construction but before occupancy
  • 14,000 cf of O/A (outside air) per sf of floor area
  • maintain 60 degrees
  • < 60% relative humidity

OR

  • if occupancy occur prior to flush out
  • delivery of 3500 cf O/A (outside air) per sf of floor area
  • ventilate at .30 cfm/sf.
  • minimum 3 hours per date until 14,000 cf/sf of O/A is delivered
  • USE MERV 13 filters for HVAC

Option 2: Air Quality Testing

  • conduct an IAQ baseline test after construction, prior to occupancy
  • use EPA Compendium of Methods for the Determination of Air Pollutants in Indoor Air.

Code:

  • EPA Compendium of Methods for the Determination of Air Pollutants in Indoor Air

Submittal Phase:

  • construction

Indoor Environmental Air Quality

BACK TO TABLE OF CONTENTS

Click here for the best Study Guides & Practice Exams

20 Comments On This Post

  1. On option 2 with occupancy rate should be 3500 CF of air per sf priot to occupancy. Per LEED NC 2.2

    Reply
  2. Thanks Brian, nice catch here.

    Reply
  3. MERV 8 filters installed prior to flush-out will satisfy this credit, EQc3.2 as well as EQc3.1.

    If the project is pursuing EQc5: Indoor Source Control, MERV 13 filters should be installed.

    Reply
  4. The distinction between when to use MERV 8 versus MERV 13 was addressed on least two of my exam questions. The information in the previous post is correct, except it should say
    …EQc5, MERV 13 (or better) MUST be installed.

    Reply
  5. I am working as the LEED Manager for a construction company that is using specs written with v2.1 to certify a building under v2.2. Yeah, its not too fun.

    Does anyone know how long a typical building flush-out takes for a 20,000 sf building under v2.2? Our specs are calling for a 2-week flush-out, and I’m afraid that the 14,000 cf of O/A per sf of floor area in v2.2 will take longer than 2 weeks, although we haven’t ran the calcs yet.

    Any advice? Please?

    Reply
  6. “During each day of the flush-out
    period, ventilation shall begin a minimum of three hours prior to occupancy and
    continue during occupancy.”
    It’ not equal to 3 hours per day

    Reply
  7. What activities can occur during a flush out?

    Reply
  8. During flush out…
    NO CLEANING
    NO PUNCH LIST

    COMMISSIONING OK IF NO ADDITIONAL CONTAMINANTS ARE INTRODUCED INTO THE BUILDING

    Reply
  9. MERV 13 is added to existing HVAC system “post construction”
    Does that mean that it has to be added for 3.2 or it has to be added only if MR 5 is carried out?

    Reply
  10. Reenu,

    A MERV 13 filter only needs to be used IF the building is pursuing EQ5. If the proejct does not need/want EQ 5, any filter that meets the design specs will work.

    Reply
  11. Is this IAQ Management Plan part of/a supplement to/the same as the one mentioned in 3.1, or is it an entirely separate document?

    Reply
  12. TwinsMommy – I was wondering the same thing about the IAQ plan. I could not find any clarification in the ref guide. My guess would be that yes it is the same plan but that the plan has two distinct parts, during construction & before occupancy.

    Regarding the discussion of MERV 8 vs. 13:

    3.1 MERV 8 req’d
    from ref “note that the req’t for MERV 13 filters has been MOVED to c5. This credit does NOT regulate the efficiency of filters used in the operation of the bldg”

    3.2 MERV 8 req’d OR MERV 13 (if pursuing c5)
    BUT for Option 1 ONLY as far as I can see, not option 2 (IAQ) as this study guide shows? Am I correct on this?

    PAT any input?

    Reply
  13. Sophia
    yes you have to replace the filter prior iaq testing as noted in page 333 of v2.2
    “projects should replace media at this point. Finally complete the air test and balancing of the HVAC systems before begining the baseline IAQ testing”
    Hope this helps

    Reply
  14. Hello,
    I am not able to get through with building flush out.
    Pre-occupied flush-out: 14000cfm OA per sq.ft. If building area is too large then flush-out time will remain same or it will change? How to decide how much time my building (1Lack sq.Ft.) will take for flush-out?
    Occupied flush-out: How to decide the flush-out time for 3500cfm OA per sq.ft until total of 14000cfm OA per sq.ft delivered.
    It says minimum 3500cfm OA per sq.ft. will it be possible to deliver higher cfm than 3500.

    Reply
  15. How to manage the ventilation rate of 0.30cfm/sq.ft for occupied flush-out.
    When i should believe the flush-out is completed for a building for both options.

    Reply
  16. hi! I passed the exam, Pat, thanks a lot for such a great web site.
    Lots of questions about leed administrative process, more than expected…
    Thanks Pat!

    Reply
  17. Hi Pat, I passed my exam for LEED CI on June30th. I have to thank you and this great website that got me started and kept me going.

    Reply
  18. Hi Pat- I passed my exam as well. Thank you SOOO MUCH for this incredible site 🙂

    -Ali

    Reply
  19. “During flush out…
    NO CLEANING
    NO PUNCH LIST

    COMMISSIONING OK IF NO ADDITIONAL CONTAMINANTS ARE INTRODUCED INTO THE BUILDING”

    I changed my answer last minute to Commisioning.

    Took the 6PM test on June 30th and passed with a 179. May be one of the last to earn LEED NC v2.2. Thanks for all the info Pat. You’ve done a great job. Your hiatus is well deserved!

    Reply
  20. Hi Pat

    IEQ 3.2 Option 2: Before Occupancy – Air Quality testing

    For IAQ testing if EPA is not known in India, can we follow NIOSH/ OSHA procedures. (for LEED CI)

    Kumar

    Reply

Leave a Comment

Please refrain from posting any exam questions that are from the actual LEED exam or other sample exams. This jeopardizes the existence of the open comment format. Such comments will be deleted. Thank you for your understanding.

(required)
(requred)

Study Guides

My recommendations for the most helpful study guides and audio books that you can find for every LEED rating system.
Click for more info....

Study Guides

Practice Exams

There are tons of practice exams available to help you study for your LEED exam. Here are the BEST practice exams you can find that I’ve personally used and recommend to anyone.
Click for more info....

Practice Exams

Continuing Education (CE) Units

This 30 hour package includes everything you need to meet the GBCI Credential Maintenance requirements for LEED APs with Specialty.

Continuing Education (CE) Units

Classes

Find out where LEED exam prep classes are being held in your local area. Training courses will help you get through the exam process quickly and easily.
Click for more info....

Classes

About Me

About Me

Hi! My name is Pat and I’m the guy behind GreenExamAcademy.com. I graduated with a B.A. in Architecture from the University of California Berkeley, and was working in an Architecture firm for the last few years in Southern California...

MORE »

Your website has been a great help and I thank you for putting a great resource tool for everyone to follow.

-Anthony

Read more Testimonials »